| To enable the silo to be removed from site quickly and to
prevent any unwanted delays with the silo remaining on site longer than
required, it is imperative that the silo legs and the silo base are kept clean
and free from obstruction, and that all accidental mortar spillages around the
silo area are cleaned up immediately before any spilt mortar has time to set.
If accidental spillages are allowed to accrue, it could mean
that the silo truck would be unable to lift the silo from the base and this would
incur a charge being levied by Remix.
Therefore please ensure that a policy of good housekeeping is
in force around the silo base area.
Please note that the silo truck will be unable to remove any
silo from site that contains more than 12 tonnes of material (34 tubs). Please
help us to help you by making sure that if a surplus of material is left in the
silo at the end of the contract, no more than 12 tonnes (34 tubs) is left in the
silo prior to the silo truck attending to facilitate removal. |